# Cedar & Finch | Weekly onboarding update

Reporting period: 9 to 13 November 2026  
Draft for Andrew’s review

Hi Maya,

You approved the kickoff checklist and the scope for a two-client pilot this week. Before I can recommend starting the pilot, we need to resolve the rehearsal status and secure your approval of the intake form.

## Decisions needed

Would you like to expand the agreed scope to include a welcome-pack walkthrough? The additional work is awaiting your approval. I requested a decision by 16 November. We haven’t agreed on that date.

## Progress this week

- You confirmed the required intake questions on 9 November. Leila finished the form draft on 12 November, and it is in internal review.
- You approved the kickoff checklist on 10 November.
- On 10 November, you approved testing the revised process with two new clients. Starting the live pilot still requires your separate approval.

## Next steps

- The intake form needs to finish internal review before it comes to you for approval. Your approval date is unconfirmed.
- I’ll ask Priya to confirm what happened with the rehearsal and correct the record.

## Risks and open questions

The task table marks the rehearsal complete on 12 November. In the meeting, Priya said it did not take place because the required participants were unavailable. No replacement date has been agreed.

The pilot target remains 20 November. Readiness depends on resolving the rehearsal status and obtaining form approval.

Thanks,  
Andrew